Calculate the required development length for a #6 rebar in 4,000 psi concrete with normal weight aggregate in a seismic application per CBC:
Correct Answer
C) 30 inches
For #6 rebar in 4,000 psi concrete in seismic applications, the development length is calculated as 30 inches to ensure proper load transfer.
Why This Is the Correct Answer
Per the California Building Code (CBC) and ACI 318, the development length for a #6 bar (0.75-inch diameter) in 4,000 psi normal-weight concrete in a seismic application is 30 inches. Seismic applications apply an additional 1.25 multiplier over the standard development length, increasing the bar's required embedment to ensure ductile load transfer during seismic events. The 30-inch figure is the CBC-recognized result for these specific conditions.
Why the Other Options Are Wrong
Option A: 24 inches
24 inches corresponds to the non-seismic or less-conservative calculation for a #6 bar. In standard (non-seismic) conditions, 24 inches may be sufficient, but the seismic multiplier (1.25×) pushes the required length beyond this value to ensure the bar does not pull out during a seismic event.
Option B: 36 inches
36 inches is excessive for a #6 bar in 4,000 psi concrete and would be more appropriate for a larger bar size (such as #8) or lower-strength concrete under seismic loading. Using 36 inches would waste material and is not the CBC-specified value for these conditions.
Option D: 18 inches
18 inches is dangerously insufficient for seismic applications. This length might apply to very small bar sizes in high-strength concrete under standard conditions but is far below the seismic requirement for a #6 bar in 4,000 psi concrete. Using 18 inches would risk catastrophic pull-out failure.
Memory Technique
For #6 rebar in 4,000 psi concrete: standard ≈ 24 inches, seismic = 24 × 1.25 = 30 inches. Remember: seismic adds 25% to development length. '#6 at 4K psi seismic = 30 inches' as a benchmark value.
More California Questions
A contractor is installing shear walls in a residence located in Seismic Design Category D. The engineer's plans call for 15/32-inch structural sheathing with 8d nails at 6 inches on center at panel edges. The contractor wants to substitute 7/16-inch OSB with the same nailing. Is this substitution acceptable?
You are reviewing plans for a mixed-use building where the ground floor will house a restaurant with commercial kitchen equipment. The architect has specified standard residential electrical requirements throughout. What Title 24 compliance issue should you identify?
According to CBC seismic provisions, what is the concept behind the 'strong column, weak beam' design philosophy?
A residence in California has 2,800 sq ft of conditioned space. The HVAC system efficiency is 16 SEER. What is the approximate Title 24 compliance margin compared to the minimum 14 SEER requirement?
You're constructing a foundation on liquefiable soils identified in a California coastal area. The geotechnical report recommends deep foundations. Which option is most commonly specified?
A contractor is installing a heat recovery ventilation (HRV) system to comply with Title 24. The system serves a 2,000 sq ft house with 3 bedrooms. What is the minimum required ventilation rate?
During construction of a basement in sandy soil conditions, you encounter groundwater at 4 feet below grade. The basement extends 8 feet below grade. What is the critical design consideration per CBC?
During a seismic retrofit project, you discover that existing concrete has a compressive strength of 2,200 psi. The engineer specifies new anchor bolts that require 2,500 psi minimum concrete strength. What is the most appropriate action?
What is the maximum allowable notch depth in a 2x10 floor joist per CBC requirements?
You're reviewing plans for a wood-framed structure in seismic design category D. The project calls for a shear wall with 15/32-inch structural sheathing and 8d nails spaced 6 inches on center at panel edges. What is the allowable shear value per the CBC?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A building site has expansive clay soil with a plasticity index of 25. According to CBC, what is the minimum recommended foundation type?
Next Question
During construction in a high seismic zone, an inspector finds #4 rebar spliced with a 20-diameter lap length in a concrete column. Is this compliant with CBC requirements?
