Calculate the mechanics lien amount a subcontractor can claim for $35,000 in unpaid work, including allowable interest at 8% annual rate over 6 months.

Correct Answer

B) $36,400

Lien amount = $35,000 + ($35,000 × 0.08 × 0.5) = $35,000 + $1,400 = $36,400

Answer Options
A
$37,100
B
$36,400
C
$37,800
D
$36,750

Why This Is the Correct Answer

Lien amount = $35,000 + ($35,000 × 0.08 × 0.5) = $35,000 + $1,400 = $36,400

Was this explanation helpful?

More sc-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.