An owner-contractor agreement (AIA A101) references AIA A201 General Conditions. During construction, there appears to be a conflict between a provision in A101 and A201. Which document typically takes precedence?
Correct Answer
B) A101 because it is the primary agreement between owner and contractor
The primary agreement (A101) typically takes precedence over incorporated documents (A201) when there are conflicts, as it represents the specific agreement between the parties.
Why This Is the Correct Answer
The primary agreement (A101) typically takes precedence over incorporated documents (A201) when there are conflicts, as it represents the specific agreement between the parties.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
