A trench is being excavated in Type B soil. If the trench is 12 feet deep, what is the maximum allowable slope ratio for the sides without additional protective systems?
Correct Answer
A) 1:1 (45 degrees)
For Type B soil, OSHA requires a maximum slope of 1:1 (45 degrees) or flatter when excavations exceed 5 feet in depth.
Why This Is the Correct Answer
OSHA 29 CFR 1926 Subpart P classifies Type B soil as moderately cohesive (e.g., angular gravel, silt, previously disturbed soil). For excavations deeper than 5 feet in Type B soil, the maximum allowable slope is 1:1 (horizontal:vertical), which equals 45 degrees. This gives the soil enough angle to remain stable without shoring or shielding.
Why the Other Options Are Wrong
Option B: 0.75:1 (53 degrees)
A 0.75:1 slope (53 degrees) is the standard for Type A soil β the most stable classification (e.g., intact hard clay). Applying a Type A slope to Type B soil creates a steeper wall that exceeds what Type B can safely support, increasing cave-in risk.
Option C: 2:1 (26.5 degrees)
A 2:1 slope (26.5 degrees) is required for Type C soil β the least stable classification (e.g., gravel, sand, submerged soil). Using Type C requirements in Type B soil means unnecessarily wide excavations; if someone confused the association and applied it as a Type B answer, it would be incorrect because the question asks for the maximum allowable slope (steepest permitted), not the most conservative option.
Option D: 1.5:1 (34 degrees)
A 1.5:1 slope (34 degrees) does not correspond to any OSHA soil classification standard for simple slope excavations. It falls between Type A and Type B requirements and is a distractor with no regulatory basis.
Memory Technique
Use the ABC ladder: **A = Aggressive slope (0.75:1)**, **B = Basic slope (1:1)**, **C = Cautious slope (1.5:1)**. The letter grade matches how cautious you need to be β C soil needs the most caution (flattest slope).
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor must remit state unemployment tax (SUTA) based on the first $15,000 of each employee's annual wages at a rate of 3.2%. For an employee earning $45,000 annually, what is the SUTA tax liability?
Next Question
A cut and fill operation requires moving 2,500 cubic yards of soil. The soil has a swell factor of 25% and a shrinkage factor of 8%. How many cubic yards must be excavated to achieve 2,500 cubic yards of compacted fill?