EstatePass
Contract AdminProcedureseasy13% of exam part

A sustainable construction project aims to achieve 75% construction waste diversion from landfills. If the project generates 200 tons of waste total, how many tons must be diverted?

Correct Answer

B) 150 tons

75% diversion means 75% of the total waste must be recycled or reused. 200 tons × 0.75 = 150 tons must be diverted from landfills.

Answer Options
A
175 tons
B
150 tons
C
125 tons
D
140 tons

Why This Is the Correct Answer

Option C is correct because waste diversion percentage is calculated by multiplying the total waste by the diversion rate. When a project aims for 75% diversion of 200 tons total waste, the calculation is straightforward: 200 tons × 0.75 = 150 tons. This means 150 tons must be recycled, reused, or otherwise diverted from landfills, while only 50 tons (25%) can go to landfills.

Why the Other Options Are Wrong

Option A: 175 tons

125 tons represents only 62.5% diversion (125 ÷ 200 = 0.625), which falls short of the required 75% diversion target.

Option C: 125 tons

175 tons represents 87.5% diversion (175 ÷ 200 = 0.875), which exceeds the stated 75% target and would be unnecessarily costly to achieve.

Memory Technique

Remember 'Three-quarters rule': 75% = 3/4, so take 3/4 of any total. For 200 tons: 200 ÷ 4 = 50, then 50 × 3 = 150 tons diverted.

Reference Hint

Florida Building Code Chapter 4 - Special Detailed Requirements Based on Use and Occupancy, Green Building Standards section, or LEED reference materials for waste management requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.