A subcontractor wants to file a mechanics lien but never had direct contact with the property owner. What must they do first under South Carolina law?
Correct Answer
D) Send preliminary notice to the owner
South Carolina requires subcontractors without direct contracts with owners to send preliminary notice before filing a mechanics lien.
Why This Is the Correct Answer
Under South Carolina's Mechanics' Lien Law (S.C. Code § 29-5-20), subcontractors who lack a direct contract with the property owner must send a preliminary notice — sometimes called a 'Notice of Furnishing' — to the owner before lien rights fully attach. This preliminary notice ensures the owner is aware of who is working on the project and protects the sub's right to later file a lien.
Why the Other Options Are Wrong
Option A: Wait 30 days after completion
Waiting 30 days after completion is not a prerequisite for filing; it is a deadline framework that applies to WHEN a lien must be filed, not a mandatory waiting period before sending preliminary notice. Confusing deadlines with prerequisites is a common error.
Option B: File the lien immediately
Filing the lien immediately, without preliminary notice, would likely render the lien defective or unenforceable. South Carolina law requires the procedural step of preliminary notice first for those without direct owner contracts.
Option C: Obtain permission from the general contractor
General contractor permission is not required by statute to file a mechanics lien. Lien rights are a legal remedy available independently; requiring GC permission would give the GC power to block subcontractor rights, which the law does not allow.
Memory Technique
Before you can LIEN, you must be SEEN — the owner must receive preliminary notice before a subcontractor with no direct contract can assert lien rights.
More South Carolina Questions
What is the maximum contract value a Tier 1 residential contractor can undertake in South Carolina?
Under South Carolina law, a contractor discovers a material defect in their work 6 months after project completion. The owner demands immediate correction. What is the contractor's legal obligation?
A contractor has 15 employees and annual payroll of $780,000. The workers compensation rate is $4.25 per $100 of payroll. What is the annual premium?
According to SC building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?
A contractor receives a stop work order from the building official. Work continues for 3 additional days before stopping. What penalty applies per South Carolina building codes?
Under South Carolina workers compensation law, which of the following employees would be exempt from coverage requirements?
Under South Carolina contractor licensing law, how many hours of continuing education are required annually for license renewal?
A Class B contractor wants to bid on a $750,000 commercial project. What must the contractor do to be eligible?
A contractor's license expires on June 30th. They submit renewal application and fees on July 15th. What additional penalty must they pay?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A Tier I contractor completes a $45,000 addition but the final cost reaches $52,000 due to change orders. What is the potential penalty?
Next Question
A contractor purchases workers compensation insurance with a $2,500 deductible. An employee injury results in $8,750 in medical costs. How much will the insurance company pay?
