A subcontractor submits a payment application for $125,000. The general contractor retains 5% and pays the subcontractor within 7 days of receiving payment from the owner. How much should the subcontractor receive?
Correct Answer
C) $118,750
Payment to subcontractor = $125,000 - ($125,000 × 5% retainage) = $125,000 - $6,250 = $118,750.
Why This Is the Correct Answer
Payment to subcontractor = $125,000 - ($125,000 × 5% retainage) = $125,000 - $6,250 = $118,750.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A contractor receives shop drawings for structural steel that show connections different from the contract drawings. What is the appropriate action?
Next Question
A contractor submits a payment application for $125,000. The contract specifies 10% retainage on all payments. What amount should the owner pay?