A contractor receives shop drawings for structural steel that show connections different from the contract drawings. What is the appropriate action?
Correct Answer
B) Submit an RFI to the architect/engineer for clarification
When shop drawings conflict with contract drawings, the contractor should submit a Request for Information (RFI) to get clarification from the design team before proceeding.
Why This Is the Correct Answer
When shop drawings conflict with contract drawings, the contractor should submit a Request for Information (RFI) to get clarification from the design team before proceeding.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
In a Guaranteed Maximum Price (GMP) contract with a $4,000,000 GMP and shared savings of 50/50, if actual costs are $3,700,000, how much does the contractor receive?
Next Question
A subcontractor submits a payment application for $125,000. The general contractor retains 5% and pays the subcontractor within 7 days of receiving payment from the owner. How much should the subcontractor receive?
