A contractor submits a payment application for $125,000. The contract specifies 10% retainage on all payments. What amount should the owner pay?
Correct Answer
A) $112,500
With 10% retainage, the owner withholds 10% of the payment application amount: $125,000 × 0.10 = $12,500. The payment amount is $125,000 - $12,500 = $112,500.
Why This Is the Correct Answer
Retainage is withheld from each payment to incentivize project completion. With 10% retainage: Amount withheld = $125,000 × 10% = $12,500. Amount paid = $125,000 − $12,500 = $112,500. This is a straightforward application of the retainage formula.
Why the Other Options Are Wrong
Option B: $137,500
$137,500 would result from ADDING 10% to the payment application amount ($125,000 + $12,500). This reverses the direction of retainage — retainage is withheld (subtracted), not added to the payment.
Option C: $115,000
$115,000 results from withholding only $10,000 (applying an 8% rate) or a simple arithmetic error. It does not correspond to a 10% retainage on $125,000.
Option D: $125,000
$125,000 represents paying the full application amount with no retainage withheld — ignoring the contract requirement entirely. Always apply the stated retainage rate.
Memory Technique
RETAINAGE = RETAINED = kept back. The owner retains (holds back) a percentage until the project is complete. Payment = Application × (1 − Retainage%). Here: $125,000 × 0.90 = $112,500.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A subcontractor submits a payment application for $125,000. The general contractor retains 5% and pays the subcontractor within 7 days of receiving payment from the owner. How much should the subcontractor receive?
Next Question
According to OSHA, how frequently must scaffolds be inspected by a competent person?
