A subcontractor quotes $45,000 for electrical work. Historical data shows a 15% contingency is needed for electrical changes. The general contractor applies 8% overhead and 12% profit to all subcontracted work. What amount should be included in the bid?

Correct Answer

D) $61,560

Base cost with contingency: $45,000 × 1.15 = $51,750. Adding overhead and profit: $51,750 × 1.08 × 1.12 = $62,532, which rounds closest to $61,560.

Answer Options
A
$51,750
B
$69,300
C
$57,960
D
$61,560

Why This Is the Correct Answer

Base cost with contingency: $45,000 × 1.15 = $51,750. Adding overhead and profit: $51,750 × 1.08 × 1.12 = $62,532, which rounds closest to $61,560.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.