A subcontractor provides a conditional lien waiver for $25,000 but the check bounces. What is the legal status of the lien waiver?
Correct Answer
B) The waiver is void and lien rights are preserved
A conditional lien waiver is only effective when the condition (payment) is satisfied. If the check bounces, the condition is not met, making the waiver void and preserving the subcontractor's lien rights.
Why This Is the Correct Answer
A conditional lien waiver is only effective when the specified condition is met. In this case, the condition is receiving payment through the $25,000 check. When the check bounces, payment has not actually been received, so the condition fails. This makes the waiver void and preserves all of the subcontractor's lien rights. The waiver cannot be enforced without the underlying condition being satisfied.
Why the Other Options Are Wrong
Option C: The waiver becomes unconditional automatically
This is incorrect because a conditional lien waiver requires the condition to be met for validity. Since the check bounced, payment was not received, so the condition failed and the waiver cannot be valid or permanent.
Option D: The waiver is valid but can be reversed within 30 days
This is wrong because the waiver is not valid at all when the condition fails. There is no 30-day reversal period - the waiver is simply void from the start when payment is not received.
Memory Technique
Remember 'No Pay, No Way' - if the payment condition isn't met (check bounces), there's no way the conditional lien waiver can be valid.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
