A subcontractor installed $18,500 worth of electrical work and filed a mechanics lien 95 days after completion. The general contractor claims the lien is invalid. Is this correct?
Correct Answer
C) No, subcontractors have 120 days to file
In South Carolina, subcontractors have 120 days from completion to file a mechanics lien, so 95 days is within the allowed timeframe.
Why This Is the Correct Answer
Option C is correct. In South Carolina, subcontractors have 120 days from the date of last furnishing labor or materials to file a mechanics lien. Filing at 95 days falls well within this 120-day window, making the lien valid. The general contractor's claim that the lien is invalid is incorrect.
Why the Other Options Are Wrong
Option A: No, there is no time limit for subcontractor liens
Incorrect. While the lien is indeed valid (making the 'No' part correct), there is a time limit for subcontractor liens in South Carolina β 120 days. This answer is wrong because it incorrectly states there is no time limit at all, which is factually inaccurate.
Option B: Yes, liens must be filed within 90 days
Incorrect. South Carolina does not impose a 90-day deadline for subcontractor mechanics liens. The actual deadline is 120 days. A 90-day rule exists in some other states but not South Carolina, making this a classic exam distractor.
Option D: Yes, liens must be filed within 60 days
Incorrect. South Carolina does not impose a 60-day deadline for subcontractor mechanics liens. A 60-day period may apply to preliminary notice requirements in some states, but it is not the lien filing deadline in South Carolina.
Memory Technique
South Carolina = 120 days for subcontractor liens. Remember: SC = 'Sixty plus Sixty' = 120. Or think: South Carolina gives you four months (roughly 120 days) to file your lien β more time than most states.
More South Carolina Questions
What is the maximum contract value a Tier 1 residential contractor can undertake in South Carolina?
Under South Carolina law, a contractor discovers a material defect in their work 6 months after project completion. The owner demands immediate correction. What is the contractor's legal obligation?
A contractor has 15 employees and annual payroll of $780,000. The workers compensation rate is $4.25 per $100 of payroll. What is the annual premium?
According to SC building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?
A contractor receives a stop work order from the building official. Work continues for 3 additional days before stopping. What penalty applies per South Carolina building codes?
Under South Carolina workers compensation law, which of the following employees would be exempt from coverage requirements?
Under South Carolina contractor licensing law, how many hours of continuing education are required annually for license renewal?
A Class B contractor wants to bid on a $750,000 commercial project. What must the contractor do to be eligible?
A contractor's license expires on June 30th. They submit renewal application and fees on July 15th. What additional penalty must they pay?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass