A subcontractor installed $18,500 worth of electrical work and filed a mechanics lien 95 days after completion. The general contractor claims the lien is invalid. Is this correct?

Correct Answer

C) No, subcontractors have 120 days to file

In South Carolina, subcontractors have 120 days from completion to file a mechanics lien, so 95 days is within the allowed timeframe.

Answer Options
A
No, there is no time limit for subcontractor liens
B
Yes, liens must be filed within 90 days
C
No, subcontractors have 120 days to file
D
Yes, liens must be filed within 60 days

Why This Is the Correct Answer

Option C is correct. In South Carolina, subcontractors have 120 days from the date of last furnishing labor or materials to file a mechanics lien. Filing at 95 days falls well within this 120-day window, making the lien valid. The general contractor's claim that the lien is invalid is incorrect.

Why the Other Options Are Wrong

Option A: No, there is no time limit for subcontractor liens

Incorrect. While the lien is indeed valid (making the 'No' part correct), there is a time limit for subcontractor liens in South Carolina β€” 120 days. This answer is wrong because it incorrectly states there is no time limit at all, which is factually inaccurate.

Option B: Yes, liens must be filed within 90 days

Incorrect. South Carolina does not impose a 90-day deadline for subcontractor mechanics liens. The actual deadline is 120 days. A 90-day rule exists in some other states but not South Carolina, making this a classic exam distractor.

Option D: Yes, liens must be filed within 60 days

Incorrect. South Carolina does not impose a 60-day deadline for subcontractor mechanics liens. A 60-day period may apply to preliminary notice requirements in some states, but it is not the lien filing deadline in South Carolina.

Memory Technique

South Carolina = 120 days for subcontractor liens. Remember: SC = 'Sixty plus Sixty' = 120. Or think: South Carolina gives you four months (roughly 120 days) to file your lien β€” more time than most states.

Was this explanation helpful?

More South Carolina Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.