A subcontractor files a lien for $18,000 on a project. The general contractor disputes $6,000 of the claim. What amount should be held in escrow pending resolution?

Correct Answer

C) $18,000

Under Michigan lien law, the full lien amount ($18,000) should be held in escrow until the dispute is resolved, regardless of the disputed portion.

Answer Options
A
$6,000
B
$24,000
C
$18,000
D
$12,000

Why This Is the Correct Answer

Under Michigan lien law, the full lien amount ($18,000) should be held in escrow until the dispute is resolved, regardless of the disputed portion.

Was this explanation helpful?

More mi-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.