EstatePass
MichiganBusinessmedium50% of exam part

A subcontractor files a construction lien in Michigan for $25,000. The property owner disputes the claim. Under Act 497, within how many days must the subcontractor file a lawsuit to enforce the lien?

Correct Answer

D) 1 year

Under Michigan's Construction Lien Act 497, a lawsuit to enforce a construction lien must be filed within 1 year of recording the lien.

Answer Options
A
2 years
B
90 days
C
6 months
D
1 year

Why This Is the Correct Answer

Under Michigan's Construction Lien Act (Act 497 of 1980), a party who has recorded a construction lien must file a lawsuit to enforce that lien within 1 year of the date the lien was recorded. Failure to file within this 1-year window causes the lien to expire and become unenforceable. The 1-year period gives the claimant adequate time to pursue litigation without leaving the lien cloud on title indefinitely.

Why the Other Options Are Wrong

Option A: 2 years

2 years is too long — Michigan's Construction Lien Act specifically provides a 1-year enforcement deadline, not 2 years. Confusing the lien enforcement period with a general contract statute of limitations (which can be 6 years for written contracts in Michigan) is a common error.

Option B: 90 days

90 days is a different deadline under Act 497 — it is the timeframe within which the lien must be RECORDED after last furnishing labor or materials, not the period to file a lawsuit to enforce it. Confusing the recording deadline with the enforcement deadline is the most common mistake on this topic.

Option C: 6 months

6 months (approximately 180 days) is not the statutory enforcement period under Act 497. This figure has no basis in Michigan construction lien law for the enforcement deadline.

Memory Technique

Think of it in two steps: '90 days to record, 1 year to fight.' Recording is quick — you must act fast (90 days). Enforcement is slower — you have a full year to go to court. Picture a 90-day sprint to file the paperwork, then a 1-year marathon to litigate.

Was this explanation helpful?

More Michigan Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.