A subcontractor files a construction lien in Michigan for $25,000. The property owner disputes the claim. Under Act 497, within how many days must the subcontractor file a lawsuit to enforce the lien?
Correct Answer
D) 1 year
Under Michigan's Construction Lien Act 497, a lawsuit to enforce a construction lien must be filed within 1 year of recording the lien.
Why This Is the Correct Answer
Under Michigan's Construction Lien Act (Act 497 of 1980), a party who has recorded a construction lien must file a lawsuit to enforce that lien within 1 year of the date the lien was recorded. Failure to file within this 1-year window causes the lien to expire and become unenforceable. The 1-year period gives the claimant adequate time to pursue litigation without leaving the lien cloud on title indefinitely.
Why the Other Options Are Wrong
Option A: 2 years
2 years is too long — Michigan's Construction Lien Act specifically provides a 1-year enforcement deadline, not 2 years. Confusing the lien enforcement period with a general contract statute of limitations (which can be 6 years for written contracts in Michigan) is a common error.
Option B: 90 days
90 days is a different deadline under Act 497 — it is the timeframe within which the lien must be RECORDED after last furnishing labor or materials, not the period to file a lawsuit to enforce it. Confusing the recording deadline with the enforcement deadline is the most common mistake on this topic.
Option C: 6 months
6 months (approximately 180 days) is not the statutory enforcement period under Act 497. This figure has no basis in Michigan construction lien law for the enforcement deadline.
Memory Technique
Think of it in two steps: '90 days to record, 1 year to fight.' Recording is quick — you must act fast (90 days). Enforcement is slower — you have a full year to go to court. Picture a 90-day sprint to file the paperwork, then a 1-year marathon to litigate.
More Michigan Questions
A Michigan contractor forms an S-Corporation. What is the maximum number of shareholders allowed?
A contractor's employee is injured on a job site in Michigan. The contractor's workers' compensation insurance has a $500 deductible per claim. The total medical costs are $12,500 and lost wages are $3,200. What is the contractor's out-of-pocket cost for this claim?
What is the minimum general liability insurance coverage amount required for Michigan residential builders?
Under Michigan Act 299, what is the consequence for a contractor who performs work outside the scope of their license classification?
A contractor discovers that a subcontractor has filed a construction lien against their project. The general contractor believes the lien is invalid. What is the primary legal mechanism to challenge the lien in Michigan?
Under Michigan Act 299, what happens if a contractor continues to work without a valid license after it expires?
Which of the following best describes the 'pay when paid' clause limitation under Michigan law?
A project has total costs of $180,000 including $75,000 labor and $105,000 materials. With workers compensation at 7.8% of labor costs and general liability at 0.4% of total costs, what are the combined insurance costs?
A Michigan contractor is forming an LLC. What is the minimum general liability insurance coverage required for residential builders under Michigan law?
Under Michigan Act 299, a contractor's license must be renewed every:
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A Michigan contractor's current insurance policy has aggregate limits of $600,000 and per-occurrence limits of $300,000. After two claims totaling $450,000, what coverage remains available?
Next Question
A contractor's employee is injured on the job, resulting in $25,000 in medical expenses and 6 weeks of lost wages at $800/week. What is the total workers' compensation claim?
