EstatePass
Contract AdminContractsmedium40% of exam part

A subcontractor discovers an error in the plans that will require additional work costing $12,000. The project is 60% complete. What is the first step the general contractor should take?

Correct Answer

D) Document the issue and notify the owner in writing

The contractor must first document the issue and notify the owner in writing before any additional work is authorized. This protects the contractor's right to compensation and follows proper change order procedures.

Answer Options
A
Immediately authorize the work to avoid delays
B
Negotiate the price with the subcontractor first
C
Issue a written change directive to the subcontractor
D
Document the issue and notify the owner in writing

Why This Is the Correct Answer

Option C is correct because proper contract administration requires immediate documentation and owner notification when plan errors are discovered. This written notification protects the general contractor's legal right to additional compensation and establishes a clear paper trail. Florida construction law and standard contract provisions (like AIA documents) require prompt written notice to preserve claims for additional time and money. Failing to notify the owner immediately can result in waiver of the contractor's right to compensation for the additional work.

Why the Other Options Are Wrong

Option B: Negotiate the price with the subcontractor first

Negotiating price with the subcontractor before notifying the owner puts the cart before the horse. The owner must first be made aware of the issue and approve any additional work before price negotiations should occur.

Option C: Issue a written change directive to the subcontractor

Authorizing work immediately without owner notification and approval can result in the contractor absorbing the $12,000 cost. This violates proper change order procedures and may breach the contract terms that require owner approval for additional work.

Memory Technique

Think 'CYA' (Cover Your Assets) - always notify the owner in writing FIRST to protect your right to payment. Never do extra work without written owner notification, or you might eat the cost.

Reference Hint

Florida Building Construction Standards - Chapter 489, Contract Administration section, and AIA Document A201 General Conditions, Article 7 (Changes in the Work)

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.