EstatePass
mi-businessMichigan Business Managementmedium

A subcontractor completes work on June 1st but doesn't file their construction lien until October 15th. Under Michigan lien law, is this lien valid?

Correct Answer

C) No, filed too late

Michigan Construction Lien Act 497 requires liens to be filed within 90 days of last furnishing labor or materials. October 15th is beyond the 90-day deadline from June 1st.

Answer Options
A
Valid but with reduced priority
B
Yes, filed within the deadline
C
No, filed too late
D
Valid only if Notice of Furnishing was served

Why This Is the Correct Answer

Michigan Construction Lien Act 497 requires liens to be filed within 90 days of last furnishing labor or materials. October 15th is beyond the 90-day deadline from June 1st.

Was this explanation helpful?

More mi-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.