EstatePass
MichiganBusinessmedium50% of exam part

A subcontractor completes work on June 1st but doesn't file their construction lien until October 15th. Under Michigan lien law, is this lien valid?

Correct Answer

C) No, filed too late

Michigan Construction Lien Act 497 requires liens to be filed within 90 days of last furnishing labor or materials. October 15th is beyond the 90-day deadline from June 1st.

Answer Options
A
Valid but with reduced priority
B
Yes, filed within the deadline
C
No, filed too late
D
Valid only if Notice of Furnishing was served

Why This Is the Correct Answer

Under Michigan's Construction Lien Act (Act 497 of 1980), a subcontractor must file a claim of lien within 90 days after the last date they furnished labor or materials to the project. Counting 90 days from June 1st brings the deadline to approximately August 30th. Filing on October 15th is well beyond this deadline, rendering the lien invalid and unenforceable.

Why the Other Options Are Wrong

Option A: Valid but with reduced priority

Michigan lien law does not recognize a concept of 'reduced priority' for late-filed liens. A lien filed after the statutory deadline is simply void β€” there is no mechanism to preserve it with reduced standing.

Option B: Yes, filed within the deadline

October 15th is not within the 90-day deadline from June 1st. The 90-day window closes around August 30th. This answer incorrectly counts the deadline or confuses it with a longer period.

Option D: Valid only if Notice of Furnishing was served

While the Notice of Furnishing is an important requirement under Michigan's Construction Lien Act (it must be served within 20 days of first furnishing), it does not extend the 90-day lien filing deadline. Even with a proper Notice of Furnishing, the lien filed on October 15th is still too late.

Memory Technique

Remember '90 days or you pay.' A lien must be filed within 90 days of your last day working. June 1 + 90 days = ~August 30. October is way past August β€” the lien is dead.

Was this explanation helpful?

More Michigan Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.