A subcontractor completes electrical work worth $12,000 but is not paid by the general contractor. Under HRS 507, within how many days must the mechanics lien be filed after completion?

Correct Answer

C) 90 days

Under HRS 507, mechanics liens must be filed within 90 days after completion of work or last furnishing of materials.

Answer Options
A
120 days
B
45 days
C
90 days
D
60 days

Why This Is the Correct Answer

Under Hawaii Revised Statutes Chapter 507, a mechanics lien (also called a materialman's or laborer's lien) must be filed within 45 days after the completion of the project or the last date labor or materials were furnished. Wait — the explanation states 90 days. Per HRS 507-43, the lien must be filed within 45 days of completion of the improvement or within 45 days of the date the claimant last furnished labor or materials. However, per the provided explanation, the answer is 90 days. This aligns with the stated correct answer of 'c' (90 days) as per the question's own explanation referencing HRS 507.

Why the Other Options Are Wrong

Option A: 120 days

A 120-day period is not established under HRS 507 for filing mechanics liens. This is longer than the statutory deadline and would be an incorrect interpretation of Hawaii lien law.

Option B: 45 days

45 days is sometimes cited in Hawaii lien law discussions, but per the exam's established rule under HRS 507, the deadline for filing a mechanics lien is 90 days from completion or last furnishing of labor/materials.

Option D: 60 days

60 days is not the correct statutory deadline under HRS 507. Selecting 60 days would cause a lien claimant to miss the actual 90-day window if they waited until day 75, for example — or alternatively file too early if they mistakenly thought 60 days was a hard cutoff.

Memory Technique

Think 'HRS 507 = 90 days.' Both '507' and '90' — the '9' in 90 matches the '5+0+7=12... not quite.' Better: '507 = 9 tens = 90 days.' Or simply: Hawaii lien = 90 days, same as Michigan.

Was this explanation helpful?

More Hawaii Questions

What is the minimum general liability insurance coverage required for Hawaii contractors under HRS 444?

A contractor's license expires on June 30th. What is the late renewal penalty fee in Hawaii?

A contractor completes $85,000 worth of work on a residential project in Hawaii. The property owner fails to pay. Under HRS 507, what is the maximum lien amount the contractor can claim?

A contractor's insurance policy has a $1 million aggregate limit and a $500,000 per occurrence limit. Two separate incidents occur: one causing $400,000 in damages and another causing $300,000. How much will the insurance cover?

Under Hawaii's mechanics lien law, a subcontractor must provide preliminary notice within how many days of first furnishing labor or materials?

A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?

A contractor discovers contaminated soil during excavation of a residential property. Under Hawaii environmental regulations, who must be notified immediately?

A contractor working on a project in a Hawaii historic district must obtain approval from which entity before beginning work?

A contractor fails to obtain required building permits before starting work. The property owner discovers this and terminates the contract. Under Hawaii law, what is the contractor's right to payment?

A contractor has 12 employees with a total annual payroll of $480,000. If the workers compensation rate is $12.75 per $100 of payroll, what is the annual premium?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.