EstatePass
hi-lawHawaii Business & Lawhard

A subcontractor completes electrical work on March 15th. The general contractor receives final payment on April 30th. Under HRS 507, what is the last day the subcontractor can file a mechanics lien?

Correct Answer

B) June 13th (90 days from work completion)

Under HRS 507, the lien filing deadline is 90 days from completion of work (March 15 + 90 days = June 13), regardless of when final payment is received.

Answer Options
A
July 30th (91 days from final payment)
B
June 13th (90 days from work completion)
C
July 29th (90 days from final payment)
D
June 14th (91 days from work completion)

Why This Is the Correct Answer

Under HRS 507, the lien filing deadline is 90 days from completion of work (March 15 + 90 days = June 13), regardless of when final payment is received.

Was this explanation helpful?

More hi-law Questions

What is the minimum general liability insurance coverage required for Hawaii contractors under HRS 444?

A contractor's license expires on June 30th. What is the late renewal penalty fee in Hawaii?

A contractor completes $85,000 worth of work on a residential project in Hawaii. The property owner fails to pay. Under HRS 507, what is the maximum lien amount the contractor can claim?

A contractor's insurance policy has a $1 million aggregate limit and a $500,000 per occurrence limit. Two separate incidents occur: one causing $400,000 in damages and another causing $300,000. How much will the insurance cover?

Under Hawaii's mechanics lien law, a subcontractor must provide preliminary notice within how many days of first furnishing labor or materials?

A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?

A contractor discovers contaminated soil during excavation of a residential property. Under Hawaii environmental regulations, who must be notified immediately?

A contractor working on a project in a Hawaii historic district must obtain approval from which entity before beginning work?

A contractor fails to obtain required building permits before starting work. The property owner discovers this and terminates the contract. Under Hawaii law, what is the contractor's right to payment?

A contractor has 12 employees with a total annual payroll of $480,000. If the workers compensation rate is $12.75 per $100 of payroll, what is the annual premium?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.