EstatePass
HawaiiBusiness & Lawhard50% of exam part

A subcontractor begins work on a Hawaii project on March 15th but doesn't receive a preliminary notice until April 2nd. Under HRS 507, when must they provide their own preliminary notice?

Correct Answer

A) Within 20 days of starting work

Under HRS 507, preliminary notices must be given within 20 days after the person first furnishes labor or materials to the project.

Answer Options
A
Within 20 days of starting work
B
By April 17th
C
Within 10 days of receiving the notice
D
By March 30th

Why This Is the Correct Answer

Option A is correct because HRS 507 ties the preliminary notice deadline to when the claimant first furnishes labor or materials, not to when they receive any notice from another party. The subcontractor started work on March 15th, so their own preliminary notice must be served within 20 days of that date — by approximately April 4th. The receipt of a notice from someone else on April 2nd is irrelevant to this calculation.

Why the Other Options Are Wrong

Option B: By April 17th

April 17th would be 15 days after April 2nd (the date the subcontractor received the notice). This option incorrectly uses the date of receiving a preliminary notice as the triggering event. The triggering event under HRS 507 is when the subcontractor first furnishes labor or materials, not when they receive someone else's notice.

Option C: Within 10 days of receiving the notice

Within 10 days of receiving the notice applies no such rule under HRS 507. The statute does not create a derivative 10-day window tied to receipt of another party's preliminary notice. This distracts by making the received notice the clock-starter.

Option D: By March 30th

March 30th would be only 15 days after the March 15th start date. While it correctly uses the work start date as the trigger, 15 days falls short of the actual 20-day window required by HRS 507.

Memory Technique

Think '20 days from Day 1 on the job.' The moment a shovel hits the ground or the first nail is driven, start your 20-day countdown. Other people's notices don't reset your clock.

Was this explanation helpful?

More Hawaii Questions

What is the minimum general liability insurance coverage required for Hawaii contractors under HRS 444?

A contractor's license expires on June 30th. What is the late renewal penalty fee in Hawaii?

A contractor completes $85,000 worth of work on a residential project in Hawaii. The property owner fails to pay. Under HRS 507, what is the maximum lien amount the contractor can claim?

A contractor's insurance policy has a $1 million aggregate limit and a $500,000 per occurrence limit. Two separate incidents occur: one causing $400,000 in damages and another causing $300,000. How much will the insurance cover?

Under Hawaii's mechanics lien law, a subcontractor must provide preliminary notice within how many days of first furnishing labor or materials?

A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?

A contractor discovers contaminated soil during excavation of a residential property. Under Hawaii environmental regulations, who must be notified immediately?

A contractor working on a project in a Hawaii historic district must obtain approval from which entity before beginning work?

A contractor fails to obtain required building permits before starting work. The property owner discovers this and terminates the contract. Under Hawaii law, what is the contractor's right to payment?

A contractor has 12 employees with a total annual payroll of $480,000. If the workers compensation rate is $12.75 per $100 of payroll, what is the annual premium?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.