A specialty trade contractor quotes $85,000 for work that typically costs $95,000. Before accepting this quote, what should the general contractor prioritize?
Correct Answer
B) Verify the subcontractor's financial stability and bonding capacity
Unusually low bids may indicate financial distress, incomplete scope understanding, or potential performance issues. Verifying financial stability protects against project delays and completion risks.
Why This Is the Correct Answer
A quote 10.5% below typical market cost is a significant red flag that warrants investigation before acceptance. The most critical risk is that a financially distressed or undercapitalized subcontractor may abandon the project mid-work, leaving the general contractor liable for completion at potentially higher cost. Verifying financial stability — including bonding capacity, credit standing, and payment history — protects the general contractor's schedule, budget, and client relationship. A subcontractor who cannot bond for the required amount is often signaling financial fragility regardless of their bid price.
Why the Other Options Are Wrong
Option A: Negotiate an even lower price to maximize profit
Negotiating an even lower price compounds the risk rather than mitigating it. If the original quote is already below market, further pressure could push the subcontractor into a loss position, increasing the probability of default, corner-cutting on quality, or project abandonment.
Option C: Require additional insurance coverage due to the low price
Requiring additional insurance addresses the symptom (risk transfer) rather than the root cause (subcontractor financial instability). Insurance covers specific incidents but does not protect against project delays, abandonment, or scope gaps caused by a sub that lacks the financial resources to complete the work.
Option D: Accept immediately to secure the competitive advantage
Accepting immediately without due diligence is the riskiest option. A competitive price advantage is worthless if the subcontractor fails to perform. The cost of a subcontractor default — including re-bidding, schedule delays, and liquidated damages — typically far exceeds any savings from the low bid.
Memory Technique
Low Bid = Look Before You Leap: an unusually low bid demands a financial health check before you commit — the 'savings' can become a liability.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
