A site requires 2,400 cubic yards of compacted fill. The soil has a shrinkage factor of 15% from bank to compacted state. How many cubic yards of material must be excavated from the borrow pit?
Correct Answer
B) 2,880 cubic yards
With 15% shrinkage, the soil compacts to 85% of its bank volume. Required bank volume = 2,400 ÷ 0.85 = 2,824 cubic yards, closest to 2,880 cubic yards.
Why This Is the Correct Answer
With 15% shrinkage, the soil compacts to 85% of its bank volume. Required bank volume = 2,400 ÷ 0.85 = 2,824 cubic yards, closest to 2,880 cubic yards.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?