EstatePass
Contract AdminPreconstructionhard27% of exam part

A roofing crew's productivity rate is 25 squares per day in good weather but drops to 18 squares per day in adverse conditions. For a 450-square roof project scheduled during hurricane season, what is the estimated duration accounting for weather delays?

Correct Answer

C) 25 days

Using reduced productivity rate for hurricane season: 450 squares ÷ 18 squares per day = 25 days. This accounts for expected weather-related delays during the vulnerable season.

Answer Options
A
30 days
B
18 days
C
25 days
D
22 days

Why This Is the Correct Answer

Option C is correct because during hurricane season, contractors must plan using the reduced productivity rate of 18 squares per day rather than the optimal 25 squares per day. The calculation is straightforward: 450 total squares ÷ 18 squares per day = 25 days. This conservative approach accounts for the expected weather delays and interruptions that are common during Florida's hurricane season from June through November.

Why the Other Options Are Wrong

Option A: 30 days

Option D (30 days) overestimates the project duration and doesn't correspond to any logical calculation using the given productivity rates of 25 or 18 squares per day.

Option D: 22 days

Option B (22 days) appears to use an incorrect productivity rate or calculation method that doesn't align with either the good weather rate (25 squares/day) or the adverse weather rate (18 squares/day) provided in the problem.

Memory Technique

Remember 'Hurricane = Harder work' - always use the lower (adverse weather) productivity rate when scheduling during Florida's hurricane season (June-November).

Reference Hint

Florida Building Code Chapter 15 - Roof Assemblies and Rooftop Structures, and project scheduling sections in construction management references

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.