A contractor needs to build a medical office building on a lot currently zoned for residential use. What must be obtained before applying for a building permit?

Correct Answer

B) Zoning variance or rezoning approval

A zoning variance or rezoning approval must be obtained to allow commercial use on residentially zoned property. Building permits cannot be issued for uses that don't comply with current zoning regulations.

Answer Options
A
State health department approval
B
Zoning variance or rezoning approval
C
Traffic impact analysis
D
Environmental impact study

Why This Is the Correct Answer

Zoning regulations control what types of uses are permitted on specific properties. Since the lot is currently zoned residential and a medical office building is a commercial use, the zoning must be changed through either a variance (minor deviation) or rezoning (complete change) before any building permits can be issued. Building departments cannot issue permits for uses that violate current zoning ordinances, making this the mandatory first step in the development process.

Why the Other Options Are Wrong

Option A: State health department approval

While an environmental impact study may be required for some developments, it is not the primary prerequisite for changing from residential to commercial use. The zoning issue must be resolved first before other studies are typically required.

Option D: Environmental impact study

A traffic impact analysis might be required during the development review process, but it's secondary to establishing the legal right to use the property for commercial purposes through proper zoning.

Memory Technique

Think 'Zone Before You Build' - zoning approval must come before any building permits can be issued for non-conforming uses.

Reference Hint

Florida Building Code Chapter 1 - Scope and Administration, or local zoning ordinance sections in reference materials

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.