A roofing contractor's productivity decreases from 25 squares per day to 20 squares per day due to hot weather conditions. If the normal crew cost is $2,000 per day, what is the cost per square under the reduced productivity?
Correct Answer
B) $100 per square
Under reduced productivity conditions: Cost per square = Daily crew cost ÷ Reduced daily production = $2,000 ÷ 20 squares = $100 per square. This demonstrates how weather and other factors can significantly impact labor productivity and costs.
Why This Is the Correct Answer
The cost per square under reduced productivity is calculated by dividing the fixed daily crew cost by the actual reduced production output. Since the crew still costs $2,000 per day but can only complete 20 squares instead of 25, each square now costs $2,000 ÷ 20 = $100. This demonstrates how external factors like weather directly impact unit costs even when labor rates remain constant.
Why the Other Options Are Wrong
Option A: $125 per square
$150 per square would result from using an incorrect production rate of approximately 13.3 squares per day ($2,000 ÷ 13.33 = $150), which significantly understates the actual reduced productivity.
Option C: $80 per square
$80 per square would be the result if you incorrectly used the normal productivity rate of 25 squares ($2,000 ÷ 25 = $80), but the question specifically asks for cost under reduced productivity conditions.
Memory Technique
Remember 'CUPS': Cost per Unit = Price ÷ Squares. When productivity goes down, cost per unit goes up - inverse relationship.
Reference Hint
Construction cost estimating chapters covering labor productivity factors and weather impact adjustments in contractor reference materials
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A subcontractor performs work on a private project but never receives a Notice to Owner form from the general contractor. Under Florida lien law, what is the subcontractor's lien rights status?
Next Question
A contractor must obtain a Certificate of Occupancy before the building can be occupied. Which entity typically issues the CO?
