A roofing contractor submits a bid of $45,000 for a project, while two other qualified contractors bid $52,000 and $54,000. As the general contractor, what should be your primary concern?
Correct Answer
C) Verify the low bidder understood the scope of work
A bid significantly lower than others (13-17% in this case) raises concerns about whether the contractor fully understood the scope, made calculation errors, or may attempt to recover costs through change orders. Verification is essential before acceptance.
Why This Is the Correct Answer
When a bid is significantly lower than others (13-17% difference here), it raises red flags about potential misunderstandings, calculation errors, or incomplete scope comprehension. The general contractor has a professional duty to verify the low bidder fully understood the project requirements before acceptance. This protects both parties from future disputes, change orders, and project delays that could result from scope misunderstandings.
Why the Other Options Are Wrong
Option A: Accept the low bid immediately to maximize profit
Accepting a questionable low bid without verification is risky and unprofessional. The apparent savings could quickly disappear through change orders, delays, or quality issues if the contractor didn't properly understand the scope or made calculation errors.
Option B: Reject all bids and re-solicit
Rejecting all bids is unnecessary and wasteful when two bids are reasonable and competitive. The issue isn't with the bidding process but with verifying one potentially problematic bid before making a decision.
Option D: Split the difference and negotiate a middle price
Negotiating a middle price ignores the underlying issue of whether the low bidder understood the scope. This approach doesn't address potential problems and could result in paying more than necessary if the low bid was actually accurate.
Memory Technique
Remember 'VERIFY before you BUY' - when bids vary significantly, always verify understanding before acceptance.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
