A residential construction project will disturb 3.2 acres and is located within 500 feet of a wetland. The contractor must obtain an NPDES permit and estimate the cost at $2,800. If permit costs are marked up 15% and included in the project bid, what amount should be included?

Correct Answer

A) $3,220

The permit cost with markup is $2,800 × 1.15 = $3,220. Since the project disturbs more than 1 acre, an NPDES permit is required, and contractors typically mark up permit costs to cover administrative time and risk.

Answer Options
A
$3,220
B
$2,800
C
$3,080
D
$3,500

Why This Is the Correct Answer

The correct answer is C) $3,220 because contractors must include markup on permit costs when bidding projects. The base NPDES permit cost of $2,800 is multiplied by 1.15 (representing the 15% markup) to account for administrative time, processing effort, and business risk. This markup is standard practice in construction bidding to ensure the contractor recovers all costs associated with obtaining permits.

Why the Other Options Are Wrong

Option B: $2,800

Option A is wrong because $2,800 represents only the base permit cost without any markup. Contractors cannot simply pass through permit costs at face value as they must account for the time, effort, and risk involved in obtaining permits.

Option C: $3,080

Option B is wrong because $3,080 would represent only a 10% markup ($2,800 × 1.10), not the specified 15% markup required in the problem. This calculation error would result in insufficient cost recovery for the contractor.

Option D: $3,500

Option D is wrong because $3,500 represents a 25% markup ($2,800 × 1.25), which exceeds the specified 15% markup in the problem. While contractors may use various markup percentages, this problem specifically states 15%.

Memory Technique

Remember 'NPDES = Never Pass Direct Expense Straight' - always add markup to permit costs in bids

Reference Hint

Florida Building Code Chapter 1 - Permits and Inspections, and NPDES permit requirements under environmental regulations section

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.