A punch list item requires replacing 12 damaged ceiling tiles at $8 per tile, plus 4 hours of labor at $45 per hour. What is the total cost to complete this punch list item?

Correct Answer

D) $276

Materials: 12 tiles × $8 = $96. Labor: 4 hours × $45 = $180. Total: $96 + $180 = $276.

Answer Options
A
$96
B
$316
C
$180
D
$276

Why This Is the Correct Answer

Materials: 12 tiles × $8 = $96. Labor: 4 hours × $45 = $180. Total: $96 + $180 = $276.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.