A contractor needs a crane for 6 months. Purchase price is $180,000, rental is $8,500/month. If the crane depreciates 20% annually and has $15,000 resale value after 6 months, what is the cost difference between renting and buying?
Correct Answer
C) Renting costs $2,000 more
Rental cost: 6 × $8,500 = $51,000. Purchase cost: $180,000 - $15,000 resale = $165,000 net cost for 6 months. However, 6-month depreciation: $180,000 × (20%/2) = $18,000. Actual ownership cost: $180,000 - ($180,000 - $18,000) = $18,000 + opportunity cost. Simplified comparison: $51,000 rental vs ~$49,000 ownership cost = ~$2,000 difference.
Why This Is the Correct Answer
Rental cost: 6 × $8,500 = $51,000. Purchase cost: $180,000 - $15,000 resale = $165,000 net cost for 6 months. However, 6-month depreciation: $180,000 × (20%/2) = $18,000. Actual ownership cost: $180,000 - ($180,000 - $18,000) = $18,000 + opportunity cost. Simplified comparison: $51,000 rental vs ~$49,000 ownership cost = ~$2,000 difference.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A punch list item requires replacing 12 damaged ceiling tiles at $8 per tile, plus 4 hours of labor at $45 per hour. What is the total cost to complete this punch list item?
Next Question
A project punch list contains 45 items. After one week, 28 items have been completed. At this completion rate, how many additional days will be needed to complete the remaining items?
