EstatePass
NASCLAEstimatingmedium18% of exam part

A project requires 2,400 square feet of drywall installation. If the labor productivity rate is 120 SF per 8-hour day per worker, and the crew consists of 3 workers, how many days will the installation take?

Correct Answer

B) 6.7 days

Daily crew production = 120 SF/day × 3 workers = 360 SF/day. Days needed = 2,400 SF ÷ 360 SF/day = 6.67 days.

Answer Options
A
5.6 days
B
6.7 days
C
20.0 days
D
8.0 days

Why This Is the Correct Answer

Daily crew production = 120 SF/day × 3 workers = 360 SF/day. Days needed = 2,400 SF ÷ 360 SF/day = 6.67 days.