A project requires 2,400 square feet of drywall installation. If a crew can install 300 square feet per day at a labor cost of $45 per hour for 8-hour days, what is the total labor cost for drywall installation?
Correct Answer
D) $2,880
Days needed: 2,400 ÷ 300 = 8 days. Total hours: 8 days × 8 hours = 64 hours. Total cost: 64 hours × $45 = $2,880.
Why This Is the Correct Answer
This is a multi-step labor cost calculation that requires finding the total time needed first, then converting to total hours, and finally multiplying by the hourly rate. The calculation correctly determines that 2,400 sq ft ÷ 300 sq ft per day = 8 days needed. Then 8 days × 8 hours per day = 64 total hours, and 64 hours × $45/hour = $2,880 total labor cost.
Why the Other Options Are Wrong
Option A: $3,600
This answer ($3,240) likely results from an error in the daily hours calculation, possibly using 9 hours per day instead of 8 hours (8 days × 9 hours × $45 = $3,240).
Option B: $2,160
This answer ($3,600) likely comes from incorrectly calculating 10 days instead of 8 days (10 days × 8 hours × $45 = $3,600), possibly from a division error in the first step.
Option C: $3,240
This answer ($2,160) appears to result from using only 6 hours per day instead of 8 hours (8 days × 6 hours × $45 = $2,160), which underestimates the actual work schedule.
Memory Technique
Remember 'DPT' - Divide by Production rate to get Time (days), then multiply by hours Per day, then by Total hourly rate
Reference Hint
Construction estimating and project management chapters covering labor productivity rates and cost calculations
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
During construction, you discover that the structural steel inspection was failed due to improper welding. What is the required next step before proceeding with work?
Next Question
What percentage contingency is typically appropriate for a well-defined commercial project during the design development phase?
