EstatePass
Contract AdminContractshard40% of exam part

A payment bond claim must be filed within how many days after the claimant's last day of work under typical bond provisions?

Correct Answer

A) 90 days

Most payment bonds require claims to be filed within 90 days after the claimant's last day of providing labor or materials. This timeframe is typically shorter than lien deadlines and must be strictly observed.

Answer Options
A
90 days
B
180 days
C
120 days
D
60 days

Why This Is the Correct Answer

Payment bond claims must typically be filed within 90 days after the claimant's last day of providing labor or materials to the project. This 90-day requirement is a standard provision found in most payment bonds and is established to provide a reasonable but limited timeframe for claimants to assert their rights. The deadline is strictly enforced by courts, and failure to file within this period generally results in the complete loss of the right to make a claim against the bond. This timeframe balances the need to give subcontractors and suppliers adequate time to file claims while also providing certainty to sureties about their potential exposure.

Why the Other Options Are Wrong

Option B: 180 days

60 days is too short and not the standard timeframe established in typical payment bond provisions for filing claims.

Option C: 120 days

120 days exceeds the standard payment bond claim filing period and confuses this deadline with other construction-related timeframes.

Option D: 60 days

180 days is far too long and may confuse this deadline with certain lien deadlines, but payment bond claims have much shorter filing requirements.

Memory Technique

Think '90 days for bond claims' - remember that bonds are 'quicker to expire' than liens, so you need to act faster (90 vs longer lien periods).

Reference Hint

Florida Construction Law and Lien Law chapter, specifically sections covering payment bonds and surety obligations

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.