EstatePass
nv-supplementNevada Business & Lawhard

A Nevada subcontractor provides $28,000 worth of electrical work but is not paid by the general contractor. Under NRS 108, what must the subcontractor do to preserve lien rights if no preliminary notice was served?

Correct Answer

B) Cannot establish lien rights without preliminary notice

Under NRS 108, subcontractors must serve preliminary notice within 20 days of first furnishing labor or materials to preserve lien rights, except in limited circumstances.

Answer Options
A
File a notice of non-payment with the county recorder
B
Cannot establish lien rights without preliminary notice
C
Serve a preliminary notice within 15 days of first work
D
File the lien immediately

Why This Is the Correct Answer

Under NRS 108, subcontractors (who are not in direct contract with the owner) must serve a preliminary notice to preserve their mechanics lien rights. If that notice was never served, the subcontractor has no valid lien claim for the work already performed. The subcontractor cannot retroactively cure the failure to serve preliminary notice — lien rights are lost for periods not covered by a timely notice.

Why the Other Options Are Wrong

Option A: File a notice of non-payment with the county recorder

A 'notice of non-payment' filed with the county recorder is not a recognized remedy under NRS 108 for a subcontractor who failed to serve preliminary notice. This option conflates different procedural steps and does not restore lost lien rights.

Option C: Serve a preliminary notice within 15 days of first work

Serving a preliminary notice within 15 days of first work is a specific deadline, but the scenario states no preliminary notice was served at all. More importantly, if the work is already complete, the 20-day window for serving preliminary notice has likely already passed, making late service ineffective for the work already performed.

Option D: File the lien immediately

Filing the lien immediately cannot substitute for the preliminary notice requirement. Under NRS 108, the right to record a lien depends on having properly served preliminary notice earlier. Filing a lien without the required preliminary notice leaves the lien legally defective and subject to dismissal.

Memory Technique

Think of preliminary notice as the 'lien entry ticket.' Without the ticket, you cannot get into the lien game no matter how much work you did. No ticket = no lien, period.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.