EstatePass
nv-supplementNevada Business & Lawmedium

A Nevada contractor completes $85,000 worth of work on a residential project. The owner fails to pay the final $12,000. Under NRS 108, what is the maximum time limit to file a mechanic's lien?

Correct Answer

D) 90 days from completion

Under NRS 108, mechanics' liens must be filed within 90 days of completion of work or delivery of materials.

Answer Options
A
120 days from completion
B
60 days from completion
C
180 days from completion
D
90 days from completion

Why This Is the Correct Answer

NRS 108 requires mechanics' liens in Nevada to be filed within 90 days of completion of work or final delivery of materials. The dollar amounts in the question ($85,000 total, $12,000 unpaid) are irrelevant to the filing deadline — they are included only as distractors.

Why the Other Options Are Wrong

Option A: 120 days from completion

120 days is not the Nevada deadline under NRS 108. It exceeds the statutory limit and would cause a contractor to lose lien rights entirely.

Option B: 60 days from completion

60 days is too short under NRS 108. While 60 days appears in some states' lien statutes, Nevada requires 90 days.

Option C: 180 days from completion

180 days has no basis in NRS 108 lien law. This figure might be confused with other construction-related deadlines (e.g., warranty periods or notice periods) but is not the lien-filing window.

Memory Technique

For Nevada: '90 days, same as CA.' Both states use 90 days from completion. The dollar amounts are red herrings — lien deadlines are time-based, not amount-based.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.