A Michigan contractor receives a Notice of Furnishing for a $150,000 commercial project. Under the Construction Lien Act, within how many days must the contractor provide notice to the property owner if they intend to preserve lien rights?
Correct Answer
A) 20 days
Under Michigan's Construction Lien Act 497, contractors must provide notice within 20 days of receiving a Notice of Furnishing to preserve their lien rights.
Why This Is the Correct Answer
Under Michigan's Construction Lien Act (Act 497), when a contractor receives a Notice of Furnishing from a subcontractor or supplier, the contractor must provide that notice to the property owner within 20 days to preserve the lien rights of the party who furnished the notice.
Why the Other Options Are Wrong
Option B: 60 days
60 days is not the correct timeframe under Michigan's Construction Lien Act for forwarding a Notice of Furnishing. This deadline is much shorter at 20 days.
Option C: 90 days
90 days is not the deadline for providing notice to the property owner after receiving a Notice of Furnishing. 90 days is associated with other lien filing timelines, not this notification step.
Option D: 30 days
30 days is longer than the actual 20-day requirement and would cause a contractor to miss the statutory deadline for protecting lien rights.
Memory Technique
20 days appears repeatedly in Michigan lien law β for Notice of Furnishing forwarding and other notice requirements. Think of '20' as Michigan's standard lien-notice number. When in doubt on Michigan notice periods, 20 days is often the answer.
More Michigan Questions
A Michigan contractor forms an S-Corporation. What is the maximum number of shareholders allowed?
A contractor's employee is injured on a job site in Michigan. The contractor's workers' compensation insurance has a $500 deductible per claim. The total medical costs are $12,500 and lost wages are $3,200. What is the contractor's out-of-pocket cost for this claim?
What is the minimum general liability insurance coverage amount required for Michigan residential builders?
Under Michigan Act 299, what is the consequence for a contractor who performs work outside the scope of their license classification?
A contractor discovers that a subcontractor has filed a construction lien against their project. The general contractor believes the lien is invalid. What is the primary legal mechanism to challenge the lien in Michigan?
Under Michigan Act 299, what happens if a contractor continues to work without a valid license after it expires?
Which of the following best describes the 'pay when paid' clause limitation under Michigan law?
A project has total costs of $180,000 including $75,000 labor and $105,000 materials. With workers compensation at 7.8% of labor costs and general liability at 0.4% of total costs, what are the combined insurance costs?
A Michigan contractor is forming an LLC. What is the minimum general liability insurance coverage required for residential builders under Michigan law?
Under Michigan Act 299, a contractor's license must be renewed every:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under Michigan law, within how many days must a contractor provide preliminary notice to preserve lien rights on a commercial project?
Next Question
A Michigan contractor operates as an LLC with 3 employees. The annual workers' compensation premium is $4,800, paid in 12 monthly installments. If the contractor adds 2 more employees mid-year, increasing the premium by 35%, what will be the adjusted monthly payment for the remaining 6 months?
