A mechanics lien has been filed against a property. The property owner wants to sell the property. What must happen to clear the lien for closing?
Correct Answer
B) Pay the lien amount or post a bond
To clear a mechanics lien for property sale, the owner must either pay the claimed amount or post a bond equal to 125% of the lien amount to discharge the lien.
Why This Is the Correct Answer
To clear a mechanics lien so a property can be sold or refinanced, the owner must either (1) pay the full claimed lien amount to satisfy and release the lien, or (2) post a surety bond equal to 125% of the lien amount to discharge the lien from the title. The bond substitutes for the property as security, allowing the sale to proceed while the underlying payment dispute is resolved separately.
Why the Other Options Are Wrong
Option A: Wait for the lien to expire
Waiting for the lien to expire is not a practical solution for a pending sale. SC mechanics liens can remain enforceable for up to six months (or longer if suit is timely filed), and no title insurer will close over an active lien. Sellers cannot simply wait.
Option C: Obtain a court order
Obtaining a court order alone does not discharge the lien. A court order might be sought as part of litigation to contest the lien's validity, but that process takes much longer than a closing timeline allows and is not the standard mechanism for clearing a lien at closing.
Option D: File a counter-claim
Filing a counter-claim is a litigation strategy that disputes the underlying debt but does not remove the lien from the title. Title companies will not close with a lien in place simply because a counter-claim has been filed.
Memory Technique
Remember 'Pay or Post': to close a sale with a lien on title, the owner must Pay the lien off or Post a 125% bond. Either action discharges the lien from the property so the deed can transfer clean.
More South Carolina Questions
What is the maximum contract value a Tier 1 residential contractor can undertake in South Carolina?
Under South Carolina law, a contractor discovers a material defect in their work 6 months after project completion. The owner demands immediate correction. What is the contractor's legal obligation?
A contractor has 15 employees and annual payroll of $780,000. The workers compensation rate is $4.25 per $100 of payroll. What is the annual premium?
According to SC building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?
A contractor receives a stop work order from the building official. Work continues for 3 additional days before stopping. What penalty applies per South Carolina building codes?
Under South Carolina workers compensation law, which of the following employees would be exempt from coverage requirements?
Under South Carolina contractor licensing law, how many hours of continuing education are required annually for license renewal?
A Class B contractor wants to bid on a $750,000 commercial project. What must the contractor do to be eligible?
A contractor's license expires on June 30th. They submit renewal application and fees on July 15th. What additional penalty must they pay?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor's annual revenue is $1,850,000. Their workers compensation insurance has a rate of $4.50 per $100 of payroll, and their annual payroll is $425,000. What is their annual workers compensation premium?
Next Question
According to South Carolina mechanics lien law, when must a general contractor provide preliminary notice to property owners?