EstatePass
NASCLAPlans & Specshard10% of exam part

A mechanical engineer specifies that HVAC equipment submittals must include seismic calculations. The equipment supplier states this will add 6 weeks to delivery. What is the contractor's best course of action?

Correct Answer

D) Immediately notify the owner and design team of the impact

The contractor should immediately notify the owner and design team of the schedule impact so they can make informed decisions about how to proceed with the project.

Answer Options
A
Find alternative equipment that doesn't require seismic calculations
B
Proceed with the delay and absorb the cost impact
C
Order equipment without seismic calculations to maintain schedule
D
Immediately notify the owner and design team of the impact

Why This Is the Correct Answer

The contractor must immediately notify the owner and design team of the schedule and potential cost impact. This satisfies the contractor's contractual duty to communicate material changes in schedule, allows the design team to evaluate whether the seismic requirement can be modified or expedited, and preserves the contractor's right to seek a time extension or additional compensation if warranted.

Why the Other Options Are Wrong

Option A: Find alternative equipment that doesn't require seismic calculations

Finding alternative equipment unilaterally substitutes a specified item without design team approval. Substitutions require an approved submittal process, and an unapproved substitution could result in rejection, rework, and liability.

Option B: Proceed with the delay and absorb the cost impact

Absorbing the delay and cost impact without notifying the owner waives the contractor's right to a time extension and additional compensation. Silence on a known impact can be construed as acceptance of the original schedule and budget.

Option C: Order equipment without seismic calculations to maintain schedule

Ordering equipment without the required seismic calculations violates the contract documents and could result in non-compliant installations, failed inspections, and significant liability — especially in a seismically active region.

Memory Technique

When in doubt on project management questions: COMMUNICATE FIRST. The contractor's job is to flag problems immediately, not solve them unilaterally. Think 'notify → evaluate → decide' as the sequence.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.