A material supplier delivers $25,000 worth of lumber to a residential project. Under SC mechanics lien law, what is the latest date they can file their lien if the project was completed on June 15th?

Correct Answer

B) September 15th

Material suppliers have 90 days from project completion to file a mechanics lien in South Carolina, making September 15th the deadline.

Answer Options
A
August 15th
B
September 15th
C
July 15th
D
December 15th

Why This Is the Correct Answer

Material suppliers have 90 days from project completion to file a mechanics lien in South Carolina, making September 15th the deadline.

Was this explanation helpful?

More sc-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.