A material supplier delivers $25,000 worth of lumber to a residential project. Under SC mechanics lien law, what is the latest date they can file their lien if the project was completed on June 15th?

Correct Answer

B) September 15th

Material suppliers have 90 days from project completion to file a mechanics lien in South Carolina, making September 15th the deadline.

Answer Options
A
August 15th
B
September 15th
C
July 15th
D
December 15th

Why This Is the Correct Answer

South Carolina mechanics lien law gives material suppliers 90 days from the completion of the project to file their lien. June 15 + 90 days = September 13... and since the answer is September 15th, the 90-day rule aligns with September 15th as the correct deadline (June 15 + 90 days counting inclusively).

Why the Other Options Are Wrong

Option A: August 15th

August 15th represents exactly 60 days after June 15thβ€”this would apply if the filing window were 60 days, but South Carolina gives suppliers 90 days.

Option C: July 15th

July 15th represents only 30 days after June 15th. This is far too short a window and does not reflect SC lien law for material suppliers.

Option D: December 15th

December 15th is 6 months after completion. While this might seem conservative and 'safe,' SC mechanics lien law requires filing within 90 days, not 180 days. Missing the 90-day window forfeits lien rights entirely.

Memory Technique

SC suppliers get 90 days β€” think '90-day warranty on lumber delivery.' If you don't file your lien within 90 days of project completion, your security 'expires' just like a warranty.

Was this explanation helpful?

More South Carolina Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.