A masonry crew's productivity is measured at 150 square feet per day per mason. If 2,400 square feet of brick veneer must be installed in 8 working days, how many masons are required?

Correct Answer

D) 2 masons

Required rate: 2,400 SF ÷ 8 days = 300 SF per day. Required masons: 300 SF per day ÷ 150 SF per mason per day = 2 masons.

Answer Options
A
3 masons
B
5 masons
C
4 masons
D
2 masons

Why This Is the Correct Answer

Required rate: 2,400 SF ÷ 8 days = 300 SF per day. Required masons: 300 SF per day ÷ 150 SF per mason per day = 2 masons.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.