EstatePass
Contract AdminProceduresmedium13% of exam part

A LEED project requires that 75% of construction waste be diverted from landfills. If a project generates 480 tons of waste and recycles 340 tons, does it meet this requirement?

Correct Answer

D) No, it only achieves 70.8% diversion

Waste diversion rate = (340 tons recycled / 480 tons total) × 100 = 70.8%. This falls short of the required 75% diversion rate for LEED compliance.

Answer Options
A
Yes, it achieves 75.8% diversion
B
No, it only achieves 68.2% diversion
C
Yes, it achieves 70.8% diversion
D
No, it only achieves 70.8% diversion

Why This Is the Correct Answer

Option B is correct because it accurately calculates the waste diversion rate as 70.8% and correctly identifies that this does not meet the LEED requirement. The calculation shows 340 tons recycled ÷ 480 tons total × 100 = 70.8%. Since 70.8% is less than the required 75%, the project fails to meet the LEED standard. The answer correctly states both the percentage achieved and that it falls short of compliance.

Why the Other Options Are Wrong

Option A: Yes, it achieves 75.8% diversion

Option A calculates the correct percentage (70.8%) but incorrectly concludes that the project meets the requirement. Since 70.8% is less than the required 75%, the project does NOT meet LEED compliance standards.

Option C: Yes, it achieves 70.8% diversion

Option D has an incorrect calculation showing 68.2% instead of the actual 70.8%. While it correctly identifies that the project doesn't meet requirements, the mathematical error makes this answer wrong.

Memory Technique

Remember 'LEED Loves 75' - LEED projects typically require 75% waste diversion. Always check if your calculated percentage meets or exceeds this threshold.

Reference Hint

Look up LEED requirements and sustainable construction practices in the Green Building/Environmental chapter of your contractor reference manual

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.