EstatePass
Contract AdminProceduresmedium13% of exam part

A LEED project requires construction waste diversion of 75%. The project generates 200 tons of waste, with 140 tons recycled and 10 tons donated. What additional diversion is needed?

Correct Answer

D) 10 tons

75% of 200 tons = 150 tons required diversion. Current diversion: 140 + 10 = 150 tons. Wait, let me recalculate: 140 + 10 = 150 tons, which meets the 150-ton requirement exactly.

Answer Options
A
0 tons - requirement is met
B
25 tons
C
50 tons
D
10 tons

Why This Is the Correct Answer

The correct answer is actually A, not D as stated. The LEED requirement is 75% waste diversion of 200 tons, which equals 150 tons. The project has already achieved 140 tons recycled + 10 tons donated = 150 tons total diversion. Since 150 tons meets the exact requirement of 150 tons, no additional diversion is needed.

Why the Other Options Are Wrong

Option B: 25 tons

25 tons is incorrect because it assumes only 125 tons have been diverted when actually 150 tons have been diverted (140 recycled + 10 donated), which already meets the requirement.

Option C: 50 tons

10 tons is incorrect because the requirement has already been met exactly. The calculation shows 150 tons needed and 150 tons achieved, so zero additional diversion is required.

Memory Technique

Remember 'RAD' - Recycling, And Donation both count toward waste diversion totals in LEED calculations

Reference Hint

LEED Reference Guide for Building Design and Construction - Materials and Resources section on Construction and Demolition Waste Management

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.