A LEED project requires construction waste diversion of 75%. The project generates 200 tons of waste, with 140 tons recycled and 10 tons donated. What additional diversion is needed?
Correct Answer
D) 10 tons
75% of 200 tons = 150 tons required diversion. Current diversion: 140 + 10 = 150 tons. Wait, let me recalculate: 140 + 10 = 150 tons, which meets the 150-ton requirement exactly.
Why This Is the Correct Answer
The correct answer is actually A, not D as stated. The LEED requirement is 75% waste diversion of 200 tons, which equals 150 tons. The project has already achieved 140 tons recycled + 10 tons donated = 150 tons total diversion. Since 150 tons meets the exact requirement of 150 tons, no additional diversion is needed.
Why the Other Options Are Wrong
Option B: 25 tons
25 tons is incorrect because it assumes only 125 tons have been diverted when actually 150 tons have been diverted (140 recycled + 10 donated), which already meets the requirement.
Option C: 50 tons
10 tons is incorrect because the requirement has already been met exactly. The calculation shows 150 tons needed and 150 tons achieved, so zero additional diversion is required.
Memory Technique
Remember 'RAD' - Recycling, And Donation both count toward waste diversion totals in LEED calculations
Reference Hint
LEED Reference Guide for Building Design and Construction - Materials and Resources section on Construction and Demolition Waste Management
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
In Florida, when liquidated damages are specified in a contract, they must be:
Next Question
During a project, the owner requests additional work valued at $35,000. The contractor verbally agrees and completes the work, but no written change order was executed. What is the contractor's position for payment?
