A house foundation is being constructed on expansive soil with a plasticity index of 35. The soil report recommends a specific moisture content be maintained. What is the primary reason for this requirement?
Correct Answer
A) To minimize future soil volume changes
Maintaining specific moisture content in expansive soils helps minimize future volume changes (swelling and shrinking) that could cause foundation movement and structural damage.
Why This Is the Correct Answer
Option A (to minimize future soil volume changes) is correct. Expansive soils contain clay minerals that absorb water and swell, then shrink when they dry out. Maintaining a consistent moisture content limits the amplitude of these volume changes, preventing the cyclic heaving and settlement that damages foundations.
Why the Other Options Are Wrong
Option B: To increase soil bearing capacity
Bearing capacity is influenced by moisture, but this is not the primary reason for moisture control in expansive soils. In fact, wetting expansive clay can reduce bearing capacity. The dominant concern is volumetric stability, not load-carrying ability.
Option C: To prevent soil liquefaction
Liquefaction is a phenomenon of saturated, loose granular soils (sands and silts) losing strength during seismic shaking. Clay-rich expansive soils with a plasticity index of 35 are not susceptible to liquefaction β this answer reflects a fundamental misunderstanding of soil behavior.
Option D: To improve soil compaction characteristics
Compaction characteristics relate to achieving maximum dry density during earthwork β a construction-phase concern. Once the foundation is placed, maintaining moisture content is about long-term volumetric stability, not improving compaction.
Memory Technique
Plasticity Index (PI) > 20 = expansive soil risk. High PI clays swell when wet, shrink when dry. Moisture control = keeping the soil at a stable moisture level so it neither swells nor shrinks. Think of it as keeping clay 'calm' β no dramatic wet/dry cycles, no dramatic volume swings.
More California Questions
A contractor is installing shear walls in a residence located in Seismic Design Category D. The engineer's plans call for 15/32-inch structural sheathing with 8d nails at 6 inches on center at panel edges. The contractor wants to substitute 7/16-inch OSB with the same nailing. Is this substitution acceptable?
You are reviewing plans for a mixed-use building where the ground floor will house a restaurant with commercial kitchen equipment. The architect has specified standard residential electrical requirements throughout. What Title 24 compliance issue should you identify?
According to CBC seismic provisions, what is the concept behind the 'strong column, weak beam' design philosophy?
A residence in California has 2,800 sq ft of conditioned space. The HVAC system efficiency is 16 SEER. What is the approximate Title 24 compliance margin compared to the minimum 14 SEER requirement?
You're constructing a foundation on liquefiable soils identified in a California coastal area. The geotechnical report recommends deep foundations. Which option is most commonly specified?
A contractor is installing a heat recovery ventilation (HRV) system to comply with Title 24. The system serves a 2,000 sq ft house with 3 bedrooms. What is the minimum required ventilation rate?
During construction of a basement in sandy soil conditions, you encounter groundwater at 4 feet below grade. The basement extends 8 feet below grade. What is the critical design consideration per CBC?
During a seismic retrofit project, you discover that existing concrete has a compressive strength of 2,200 psi. The engineer specifies new anchor bolts that require 2,500 psi minimum concrete strength. What is the most appropriate action?
What is the maximum allowable notch depth in a 2x10 floor joist per CBC requirements?
You're reviewing plans for a wood-framed structure in seismic design category D. The project calls for a shear wall with 15/32-inch structural sheathing and 8d nails spaced 6 inches on center at panel edges. What is the allowable shear value per the CBC?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
What is the maximum spacing allowed for transverse reinforcement (ties) in concrete columns located in seismic design category D per the CBC?
Next Question
A reinforced concrete beam requires #8 rebar with a development length of 48 inches. Due to space constraints, you can only provide 36 inches of straight development length. What is an acceptable solution per CBC?