EstatePass
GeorgiaGA Supplementmedium100% of exam part

A homeowner refuses to pay a contractor's final invoice of $12,000. The contractor wants to file a lien. What document must be filed first in Georgia?

Correct Answer

D) Notice to Owner

In Georgia, contractors must first file a Notice to Owner before they can file a valid lien claim.

Answer Options
A
Claim of Lien
B
Preliminary Notice
C
Notice of Intent to Lien
D
Notice to Owner

Why This Is the Correct Answer

In Georgia, a contractor must serve a 'Notice to Owner' (also called a Preliminary Notice) before they can perfect a mechanics lien. This notice informs the property owner that the contractor is working on the property and preserves the right to file a lien claim later.

Why the Other Options Are Wrong

Option A: Claim of Lien

The Claim of Lien is filed after the Notice to Owner step, not before it. Filing a Claim of Lien without the prior Notice to Owner renders the lien invalid in Georgia.

Option B: Preliminary Notice

Preliminary Notice is terminology used in other states (e.g., California). Georgia uses the term 'Notice to Owner' for the required preliminary document.

Option C: Notice of Intent to Lien

A Notice of Intent to Lien is not a required step under Georgia lien law. It may exist in other states' processes but is not a recognized prerequisite in Georgia's mechanics lien procedure.

Memory Technique

Georgia liens: Owner First, Claim Second. You must tell the Owner before you can Claim. 'Notice to Owner' → wait → 'Claim of Lien.' The owner always gets notified first.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.