A geotechnical report recommends drilled piers extending 25 feet below grade for a commercial building. The report cites 'potential liquefaction' as the primary concern. What soil condition is most likely present?
Correct Answer
C) Saturated loose sand
Liquefaction typically occurs in saturated, loose to medium-dense granular soils (sands and silts) during seismic events, requiring deep foundations to reach stable bearing strata.
Why This Is the Correct Answer
Liquefaction is a phenomenon that occurs when saturated, loose to medium-dense granular soils (primarily loose sand, sometimes silty sand) temporarily lose their shear strength during seismic shaking. The water pressure in the saturated voids increases to the point where soil particles behave like a liquid. Deep drilled piers are specified to bypass the liquefiable layer and anchor into stable bearing strata below.
Why the Other Options Are Wrong
Option A: Expansive clay
Expansive clay swells and shrinks with moisture changes, causing heave and settlement β but this is not liquefaction. Clays are cohesive and do not liquefy during earthquakes.
Option B: Bedrock at shallow depth
Bedrock at shallow depth is actually a desirable foundation condition providing excellent bearing capacity. It is the opposite of a liquefaction concern and would not require deep piers for seismic reasons.
Option D: Organic peat
Organic peat is a problematic soil due to its compressibility and long-term consolidation settlement, but peat does not liquefy. Peat is organic, highly compressible, and unsuitable for direct bearing, but the mechanism of failure is settlement, not liquefaction.
Memory Technique
Liquefaction = 'Liquid Sand' β saturated loose sand acts like liquid during an earthquake. The word 'liquefaction' contains 'liquid,' which reminds you of water-saturated, granular (sandy) soil.
More California Questions
A contractor is installing shear walls in a residence located in Seismic Design Category D. The engineer's plans call for 15/32-inch structural sheathing with 8d nails at 6 inches on center at panel edges. The contractor wants to substitute 7/16-inch OSB with the same nailing. Is this substitution acceptable?
You are reviewing plans for a mixed-use building where the ground floor will house a restaurant with commercial kitchen equipment. The architect has specified standard residential electrical requirements throughout. What Title 24 compliance issue should you identify?
According to CBC seismic provisions, what is the concept behind the 'strong column, weak beam' design philosophy?
A residence in California has 2,800 sq ft of conditioned space. The HVAC system efficiency is 16 SEER. What is the approximate Title 24 compliance margin compared to the minimum 14 SEER requirement?
You're constructing a foundation on liquefiable soils identified in a California coastal area. The geotechnical report recommends deep foundations. Which option is most commonly specified?
A contractor is installing a heat recovery ventilation (HRV) system to comply with Title 24. The system serves a 2,000 sq ft house with 3 bedrooms. What is the minimum required ventilation rate?
During construction of a basement in sandy soil conditions, you encounter groundwater at 4 feet below grade. The basement extends 8 feet below grade. What is the critical design consideration per CBC?
During a seismic retrofit project, you discover that existing concrete has a compressive strength of 2,200 psi. The engineer specifies new anchor bolts that require 2,500 psi minimum concrete strength. What is the most appropriate action?
What is the maximum allowable notch depth in a 2x10 floor joist per CBC requirements?
You're reviewing plans for a wood-framed structure in seismic design category D. The project calls for a shear wall with 15/32-inch structural sheathing and 8d nails spaced 6 inches on center at panel edges. What is the allowable shear value per the CBC?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A homeowner wants to add a 400 square foot addition to their existing residence. The local building department requires Title 24 compliance for the entire house. What must be upgraded if the existing windows don't meet current standards?
Next Question
A residential building in California has a floor area of 2,400 square feet with R-30 ceiling insulation and dual-pane windows. What is the maximum allowable fenestration area under Title 24 for Climate Zone 3?