A Georgia contractor completes work valued at $8,500 and is not paid. How many days after completion of work does the contractor have to file a lien claim?

Correct Answer

A) 90 days

Under Georgia lien law, contractors have 90 days from completion of work to file a lien claim to protect their right to payment.

Answer Options
A
90 days
B
60 days
C
30 days
D
120 days

Why This Is the Correct Answer

Under Georgia's lien law (O.C.G.A. § 44-14-361), a contractor has 90 days from the completion of the work (or the last furnishing of labor, services, or materials) to file a claim of lien. Missing this deadline results in permanent loss of lien rights, leaving the contractor with only contractual or collections remedies.

Why the Other Options Are Wrong

Option B: 60 days

60 days is not the Georgia lien filing deadline. This number may be confused with deadlines in other states or with different Georgia notice requirements. The correct deadline is 90 days.

Option C: 30 days

30 days is far too short and is not the Georgia lien filing deadline. A 30-day window might be confused with preliminary notice requirements in some states, but Georgia's lien filing deadline is 90 days.

Option D: 120 days

120 days exceeds the Georgia statutory deadline of 90 days. A contractor who waits 120 days has already lost lien rights and cannot file a valid claim. The dollar amount ($8,500) in this question is a distractor — the filing deadline is the same regardless of the amount.

Memory Technique

Think of Georgia lien law as '90 days or you're done.' From the last day of work, count 90 days — that's your lien filing deadline in Georgia.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.