EstatePass
Contract AdminPreconstructionmedium27% of exam part

A general contractor receives three subcontractor bids for electrical work: $125,000, $142,000, and $98,000. What should be the contractor's primary concern regarding the lowest bid?

Correct Answer

D) The bid may contain errors or omissions

When a bid is significantly lower than others (in this case, $98,000 vs. $125,000 and $142,000), the primary concern should be potential errors or omissions in the estimate. A bid that's substantially lower may indicate the subcontractor missed scope items or made calculation errors.

Answer Options
A
The electrical contractor lacks proper licensing
B
The materials specified are of inferior quality
C
The project schedule will be extended
D
The bid may contain errors or omissions

Why This Is the Correct Answer

When one bid is significantly lower than others (in this case $98,000 compared to $125,000 and $142,000), the primary concern should be potential errors or omissions in the estimate. A 22-28% difference from the other bids is a red flag that suggests the subcontractor may have missed scope items, made calculation errors, or failed to include all required work. This could lead to change orders and cost overruns during construction. The general contractor has a duty to investigate unusually low bids before acceptance.

Why the Other Options Are Wrong

Option A: The electrical contractor lacks proper licensing

Material quality concerns are not necessarily indicated by a low bid amount alone. The specifications should clearly define material requirements, and all bidders should be pricing to the same specifications. Material quality issues would require specification review rather than bid amount analysis.

Option C: The project schedule will be extended

A lower bid amount does not inherently indicate schedule extension issues. In fact, a lower bid might suggest faster completion if the contractor has better efficiency or lower overhead. Schedule concerns should be evaluated separately from bid pricing through schedule submittals and contractor capacity analysis.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.