EstatePass
South CarolinaSC Supplementmedium100% of exam part

A general contractor in South Carolina must file a mechanics lien claim within how many days of the last work performed or materials supplied?

Correct Answer

B) 120 days

South Carolina mechanics lien law requires filing within 120 days of the last work performed or materials supplied.

Answer Options
A
150 days
B
120 days
C
60 days
D
90 days

Why This Is the Correct Answer

South Carolina Code of Laws Section 29-5-90 requires that a mechanics lien be filed within 90 days of the last work performed or materials furnished for subcontractors and materialmen, and within 120 days for general contractors. This question specifies a general contractor, making 120 days the correct answer.

Why the Other Options Are Wrong

Option A: 150 days

150 days exceeds the South Carolina statutory deadline. Filing after 120 days (for a GC) would result in a time-barred lien that cannot be enforced.

Option C: 60 days

60 days is the filing deadline in some other states (notably shorter-deadline jurisdictions) but is not South Carolina's requirement for general contractors. Confusing state-specific deadlines is a common exam error.

Option D: 90 days

90 days is the South Carolina deadline for subcontractors and materialmen β€” not for general contractors. This is the most tempting wrong answer because the 90-day figure is real but applies to a different tier of claimant.

Memory Technique

SC GC lien = 120 days (4 months). Subs get 90 days (3 months). GC gets a longer runway because they coordinate the whole project. '4 months for the GC, 3 months for the sub.'

Was this explanation helpful?

More South Carolina Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.