A general contractor discovers that actual job costs are running 15% over budget on a $2.8 million project that is 60% complete. If the trend continues, what will be the total cost overrun at project completion?
Correct Answer
C) $420,000
If costs are 15% over budget for the entire project: $2,800,000 × 15% = $420,000 total overrun. The percentage complete doesn't change the total projected overrun if the trend continues.
Why This Is the Correct Answer
If costs are running 15% over budget and this trend continues for the entire project, the total overrun at completion is simply 15% of the total project budget: $2,800,000 × 15% = $420,000. The 60% completion figure is provided as a distractor — if the 15% overrun trend applies to the whole project, the percentage complete does not change the total projected overrun.
Why the Other Options Are Wrong
Option A: $700,000
$700,000 represents 25% of $2,800,000, which has no basis in the given data. This may result from incorrectly applying a combined overhead and profit factor rather than using the stated 15% overrun rate.
Option B: $168,000
$168,000 results from calculating 15% of only the costs incurred so far (60% of $2,800,000 = $1,680,000 × 10% = $168,000), which misunderstands the question. The question asks for the total overrun at project completion if the trend continues, not the current dollar overrun to date.
Option D: $252,000
$252,000 is 15% of $1,680,000 (the 60% already spent), representing only the overrun on work completed so far — not the projected total overrun at completion. This ignores the remaining 40% of the project where the same trend is expected to continue.
Memory Technique
For 'if the trend continues' cost overrun questions, apply the overrun percentage to the TOTAL project budget — not just the work done so far. Think of it as: trend × total = total overrun. The percentage complete is only a distractor when the trend applies to the whole job.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
