EstatePass
Contract AdminContractsmedium40% of exam part

A dispute arises between the contractor and owner over a $25,000 change order. The contract specifies mediation before arbitration. The owner wants to proceed directly to litigation. What should happen?

Correct Answer

A) The parties must first attempt mediation as specified in the contract

When a contract specifies a dispute resolution procedure, the parties are typically bound to follow that procedure. Mediation must be attempted first before proceeding to arbitration or litigation.

Answer Options
A
The parties must first attempt mediation as specified in the contract
B
The case can go directly to court since the amount exceeds $20,000
C
Arbitration must be conducted before any court action
D
The owner can choose litigation since they are the paying party

Why This Is the Correct Answer

CORRECT_ANSWER - When parties enter into a contract that specifies a particular dispute resolution procedure, they are legally bound to follow that agreed-upon process. The contract clearly states that mediation must occur before arbitration, creating a mandatory sequence that both parties must honor. Neither the dollar amount of the dispute nor the preferences of either party can override the contractual obligation to attempt mediation first. Courts will typically enforce these dispute resolution clauses and may dismiss cases that don't follow the prescribed procedure.

Why the Other Options Are Wrong

Option B: The case can go directly to court since the amount exceeds $20,000

While the contract does specify arbitration after mediation, the question asks what should happen first. The parties must attempt mediation before proceeding to arbitration, making mediation the immediate required step.

Option C: Arbitration must be conducted before any court action

The dollar amount of a dispute does not override contractual dispute resolution requirements. There is no legal threshold that allows parties to bypass agreed-upon mediation procedures based on the monetary value of the claim.

Option D: The owner can choose litigation since they are the paying party

Neither party, regardless of their role as owner or contractor, can unilaterally choose to ignore contractual dispute resolution procedures. The paying party does not have special rights to bypass agreed-upon mediation requirements.

Memory Technique

Remember 'Contract Controls' - when a contract specifies dispute steps, those steps control the process, not external factors like money amounts or party wishes.

Reference Hint

Florida Building Code - Chapter 1, General Provisions, or Construction Contract Law sections dealing with dispute resolution procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.