EstatePass
TennesseeTN Supplementmedium100% of exam part

A contractor's total project cost is $65,000 with materials costing $24,000. If the workers' compensation rate is $3.20 per $100 of labor cost, what is the workers' compensation premium?

Correct Answer

C) $1,312.00

Labor cost = $65,000 - $24,000 = $41,000. Premium = ($41,000 ÷ $100) × $3.20 = 410 × $3.20 = $1,312.00

Answer Options
A
$768.00
B
$1,024.00
C
$1,312.00
D
$2,080.00

Why This Is the Correct Answer

Labor cost = Total project cost − Materials = $65,000 − $24,000 = $41,000. Workers' comp premium = (Labor cost ÷ $100) × Rate = ($41,000 ÷ $100) × $3.20 = 410 × $3.20 = $1,312.00. The premium is calculated on labor only, not total project cost.

Why the Other Options Are Wrong

Option A: $768.00

$768.00 results from incorrectly using only the materials cost as the base: ($24,000 ÷ $100) × $3.20 = $768. This is the opposite error — applying the rate to materials instead of labor.

Option B: $1,024.00

$1,024.00 does not correspond to any correct calculation path. It may result from rounding errors or using an incorrect labor figure (approximately $32,000 as the labor base, which is not derived correctly).

Option D: $2,080.00

$2,080.00 results from applying the rate to the entire project cost without subtracting materials: ($65,000 ÷ $100) × $3.20 = $2,080. This is the most common error — forgetting that workers' comp is based on labor cost only.

Memory Technique

Workers' comp = workers' pay = LABOR only. The formula is: (Total − Materials) = Labor, then (Labor ÷ 100) × Rate = Premium. Write it as a fraction: Labor/100 × Rate. For this problem: 41,000/100 × 3.20 = 410 × 3.20 = $1,312.

Was this explanation helpful?

More Tennessee Questions

Calculate the Tennessee workers' compensation premium for a roofing contractor with a $180,000 annual payroll and a rate of $28.50 per $100 of payroll:

How many hours of continuing education are required for Tennessee contractor license renewal?

Calculate the workers' compensation experience modification factor for a contractor with $85,000 in expected losses and $68,000 in actual losses:

Under Tennessee lien law, what is the maximum time limit to enforce a mechanics lien after it has been filed?

Under Tennessee lien law, which party has priority when multiple liens are filed against the same property?

Under Tennessee building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?

A homeowner in Nashville hires an unlicensed contractor for $8,000 worth of electrical work. The contractor demands payment but the work fails inspection. Under TCA 62-6, what recourse does the unlicensed contractor have?

Under Tennessee building codes, what is the minimum ceiling height required for habitable rooms in residential construction?

A Tennessee contractor has 8 employees working on a residential project. The total weekly payroll is $6,400. If the workers' compensation rate for residential construction is $8.50 per $100 of payroll, what is the weekly workers' compensation premium?

A contractor is installing a septic system for a new home in rural Tennessee. The estimated cost is $8,500. According to TCA 62-6, what licensing requirement applies?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.