A contractor's insurance policy has a $500,000 general liability limit with a $1,000 deductible. A claim is filed for $15,000 in damages. How much will the contractor pay out of pocket?
Correct Answer
D) $1,000
The contractor pays the $1,000 deductible, and insurance covers the remaining $14,000 since the claim is within policy limits.
Why This Is the Correct Answer
The deductible is the contractor's out-of-pocket responsibility on each claim. With a $1,000 deductible and a $15,000 claim that is well within the $500,000 policy limit, the contractor pays $1,000 and the insurance company covers the remaining $14,000. The policy limit is not a factor here since $15,000 is far below $500,000.
Why the Other Options Are Wrong
Option A: $14,000
$14,000 is the amount the insurer pays, not the contractor. This answer reverses the contractor's and insurer's responsibilities.
Option B: $0
$0 would be the contractor's cost only if there were no deductible. A $1,000 deductible means the contractor always pays the first $1,000 of any covered claim.
Option C: $15,000
$15,000 would be the contractor's total exposure only if they had no insurance or if the claim exceeded the policy limit. Neither condition applies here β the policy is active and the claim is well within limits.
Memory Technique
Deductible = 'D for Down payment on the claim.' The contractor always pays the deductible first, then insurance covers the rest up to the limit. Formula: Contractor pays = Deductible (when claim > deductible and < policy limit).
More South Carolina Questions
What is the maximum contract value a Tier 1 residential contractor can undertake in South Carolina?
Under South Carolina law, a contractor discovers a material defect in their work 6 months after project completion. The owner demands immediate correction. What is the contractor's legal obligation?
A contractor has 15 employees and annual payroll of $780,000. The workers compensation rate is $4.25 per $100 of payroll. What is the annual premium?
According to SC building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?
A contractor receives a stop work order from the building official. Work continues for 3 additional days before stopping. What penalty applies per South Carolina building codes?
Under South Carolina workers compensation law, which of the following employees would be exempt from coverage requirements?
Under South Carolina contractor licensing law, how many hours of continuing education are required annually for license renewal?
A Class B contractor wants to bid on a $750,000 commercial project. What must the contractor do to be eligible?
A contractor's license expires on June 30th. They submit renewal application and fees on July 15th. What additional penalty must they pay?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A specialty contractor completes $28,000 of plumbing work but is not paid. They file a mechanics lien for the full amount plus $3,200 in attorney fees. What is the maximum lien amount allowable under South Carolina law?
Next Question
A contractor in South Carolina completes $85,000 worth of work but has not been paid. If they file a mechanics lien, what is the maximum amount they can claim?